Branch Drive Culvert Guardrail Update 8/6/19

Recent Facebook posts are inaccurate, misleading and lacking in facts – residents are encouraged to reach out to the mayor for accurate information regarding the NE Branch restoration and culvert work. The village is well aware of the dissatisfaction regarding…

Culvert Update July

Next week work will be starting approximately on Monday July 29 in Area 2-  Terrace Drive. This means Terrace Drive will be closed and Branch Drive will be reopen. We are hopeful things will be smoother this time around. Fingers…

Culvert Update 5-16-19

Thank you in advance for being patient during this long process of NE Branch / Culvert restoration. We are in constant communication with the County and with the lead Engineer (Nestor Tan) on the project. They are aware of our…

Village Hall Renovations Underway

The Village Hall is temporary located at 180 E. Main Street Suite 103, Smithtown, NY.  Not far at all, its diagonally across the street. We are currently renovating the Village Hall and should be done in the beginning of June….

May 2019 Planning Board Meeting Changed

Please be advised the May Planning Board meeting scheduled for May 15th, has been changed to the following Wednesday May 22nd at 7:30 at 180 E. Main Street Suite 103. This is our temporary location due to Village Hall renovations.

Culvert Update 2/28/19

Just received word from Leslie Kennedy that PSEG has completed the temporary work at the first culvert and the Contractor is telling us that they will be back on site this coming Monday March 4th. The second culvert is presently…

In Memorium………..

It is with deepest regret that we announce the passing of Jerry Harris. Jerry was our Building Inspector for 19 years and was a friend to numerous mayors and board members. Residents were blessed to have him as a resource…

Culvert work update!

Just received an updated projected schedule as of January 15th 2019 of work being done at the culverts. 1. Culvert sections will be delivered week of January 21st. Work at Branch Drive is projected to be substantially completed by second…