Culvert work update!

Just received an updated projected schedule as of January 15th 2019 of work being done at the culverts.

  • 1. Culvert sections will be delivered week of January 21st. Work at Branch Drive is projected to be substantially completed by second week of February. Final paving will be subject to seasonal temperature limitations and may be done at a later date.
  • 2. Work at Terrace lane will follow and is projected to be substantially completed by the end of March. Final paving will be subject to seasonal temperature limitations and may be done at a later date.
  • 3. River bed sediment removals is next, and projected to finish by the end of April.