Good News……………….NE Branch work to begin Oct 1, 2018

Wanted to share the great news that the long awaited NE Branch Culvert Project is set to begin October 1st 2018. The starting point for location 1 is the culvert at Branch Drive. As they progress location 2 is the culvert at Terrace Lane and the follow up will be with cleanup work at Location 3 NYS111 and Location 4 in the stream just North of RT 347.

SCWA will be on site shortly to cap off one or more water mains that are within the excavation for the culverts.

Residents within the general vicinity will be provided a notice of work as well as notification to emergency services when each section of the road will be closed. To be very clear, when they begin each of the culvert locations, the road will be impassible for the duration of the work. They will, however, be completed independently so there will never be more than one crossing closed at a time. Without any unforeseen conditions, the project should be complete late winter of 2019.